Research: The Energy Infrastructure of the AI Boom

Three Mile Island restarting for Microsoft, Talen and Amazon at Susquehanna, the SMR deals, PJM and ERCOT grid stress, rate shocks, data-center water, xAI's Memphis turbines, Stargate, and the Gulf money underneath the compute.

2026-11-15 30 min read Research file
Contents

The physical-infrastructure companion to The Financialization of Frontier AI (where the capital gets traced) and Palantir, Architecture and Contracts (where the control-grid software gets traced). This file traces the electrons — the grids, reactors, gas turbines, water rights, and sovereign-fund infrastructure deals that physically underwrite the compute that runs the models that run the safety theater that runs the control grid.

Sourcing standard: defamation-audit grade. Primary sources first (FERC orders, NRC filings, IEA / Lawrence Berkeley reports, state PUC orders, hyperscaler sustainability reports, company press releases, state utility filings). Secondary press is attributed where the primary trail is not yet public, or where a regulator’s filing is paywalled or buried in docket-level PDFs. No editorial framing (“greenwashing,” “land grab,” “guzzling”) is adopted as voice; such characterizations are quoted and attributed.

All MW / GW values are nameplate or contracted unless noted. Currency USD.

The load-bearing claim here is that the AI buildout has a physical dimension that the safety-and- alignment discourse routinely ignores. The reactor that defined American nuclear fear (1979 AD) is restarting (2027 AD) to power inference workloads owned by the second-largest equity-method holder in OpenAI. The grid that serves the federal-data-center cluster in Northern Virginia has just been reauthorized to charge data-center loads as a separate rate class because residential ratepayers were absorbing the capacity cost. Texas is processing 233 GW of interconnection requests, 70% of them data centers, against ~23 GW of new generation in the same build cycle. A 422 MW gas-turbine fleet in South Memphis is in violation of the Clean Air Act because the alternative was waiting months for grid power. The Three Mile Island Unit 2 spent fuel — the one that melted in 1979 — is still in dry-cask storage on site.

That is the physical receipt that the singleton runs on. The financialization dossier shows who pays for the buildout. This one shows what gets built, where, and at whose expense.


1. Hyperscaler Nuclear Deals (2024-2026)

The 2024-2026 cycle is the first time since the Three Mile Island accident (28 March 1979 AD) that American corporates have signed PPAs contingent on restarting decommissioned reactors or building new reactors at scale. Four named hyperscalers have five named transactions on the public record as of May 2026.

1.1 Microsoft × Constellation Energy — Three Mile Island Unit 1

  • Announcement: 20 September 2024. 20-year power purchase agreement between Microsoft and Constellation Energy under which Microsoft purchases 100% of the output of the restarted Three Mile Island Unit 1 reactor. Source: Constellation press release, “Constellation to Launch Crane Clean Energy Center” (constellationenergy.com).
  • Contracted capacity: 835 MW nameplate. Source: Constellation press release (above); DCD coverage (DatacenterDynamics).
  • Renamed asset: Three Mile Island Nuclear Station, Unit 1 renamed “Christopher M. Crane Clean Energy Center” (CCEC) under NRC Amendment No. 306 to Renewed Facility License No. DPR-50, approved 13 May 2025. Source: NRC info-finder page for CCEC (nrc.gov).
  • Capital cost: ~$1.6 billion to restore the plant to operational condition. Source: Constellation; Utility Dive (utilitydive.com).
  • Federal financing: $1 billion DOE loan guarantee announced November 2025 (Title 17 Innovative Clean Energy Loan Program). Source: NucNet, “Constellation Secures $1 Billion Federal Loan For Three Mile Island Restart” (nucnet.org).
  • Restart date: Originally targeted 2028, now accelerated to 2027. Source: Constellation, “One Year Later: Crane Clean Energy Center Still in the Spotlight and Ahead of Schedule” (constellationenergy.com).
  • NRC docket status: Constellation submitted its Environmental Report supporting resumption of power operations on 31 October 2025. Three Mile Island Alert filed a Petition to Intervene citing absence of off-site emergency plans and radiation monitors since 2019 shutdown. Source: NRC (nrc.gov); Pennsylvania Capital-Star (penncapital-star.com).
  • Tax-credit eligibility: CCEC certified eligible for the 45Y Clean Electricity Production Credit (Inflation Reduction Act). Source: Constellation press release (above).
  • License-extension request: Constellation separately filed for renewal extending plant operations to at least 2054.

1.2 Amazon × Talen Energy — Susquehanna

  • Initial transaction: March 2024. Amazon acquired the 960-acre Cumulus Data Centers campus adjacent to the Susquehanna nuclear power plant from Talen Energy for $650 million. The campus is designed for behind-the-meter power supply from the 2.5 GW Susquehanna plant.
  • Original ISA filing: Talen and PJM submitted an amended Interconnection Service Agreement (ISA) to FERC in 2024 to raise co-located load capacity from 300 MW to 480 MW. Source: Talen Energy IR press (ir.talenenergy.com).
  • FERC rejection: 1 November 2024. FERC voted 2-1 to reject the amended ISA on the basis that Talen and PJM did not demonstrate that the expanded behind-the-meter arrangement was just and reasonable under section 205 of the Federal Power Act. Commissioners Christie and See in majority; Chair Willie Phillips in dissent. Source: ANS Nuclear Newswire (ans.org); Pillsbury legal analysis (pillsburylaw.com).
  • Phillips dissent language: Called the decision “a step backward for both electric reliability and national security.”
  • Counterparty objections: American Electric Power and Exelon filed protests arguing that behind-the-meter arrangement would let data-center loads “derive benefits from the transmission system without paying for them.” Source: ANS Nuclear Newswire (above).
  • Rehearing: 16 April 2025. FERC affirmed rejection on rehearing, same 2-1 split. Source: ANS Nuclear Newswire (ans.org).
  • Litigation: Talen filed suit in the Fifth Circuit Court of Appeals on 28 January 2025. Source: Power Engineering (power-eng.com).
  • Restructured deal (June 2025): Talen and Amazon announced a restructured front-of-the-meter arrangement: a 17-year, approximately $18 billion power purchase agreement supplying up to 1,920 MW of carbon-free electricity from Susquehanna, with deliveries beginning in 2026 and ramping through 2032. Source: Utility Dive, (utilitydive.com).
  • FERC follow-on rulemaking: On 18 December 2025 FERC issued an order directing PJM to develop new tariff rules governing co-located load and Behind-the-Meter Generation arrangements, proposing two new transmission services (Firm Contract Demand and Non-Firm Contract Demand). Source: FERC Fact Sheet (ferc.gov); Baker Botts (bakerbotts.com).

1.3 Google × Kairos Power — SMR fleet

  • Announcement: 14 October 2024. First corporate agreement for multiple deployments of a single advanced reactor design in the United States. Source: Google blog (blog.google); Kairos Power press (kairospower.com).
  • Total contracted capacity: Up to 500 MW across multiple reactor deployments. First reactor targeted online by 2030, with additional deployments through 2035.
  • Reactor design: Kairos KP-FHR — fluoride-salt-cooled, high-temperature reactor using TRISO pebble fuel. Commercial configuration: dual-unit plants at 75 MWe each (150 MWe per plant). Source: Kairos Power; World Nuclear News (world-nuclear-news.org).
  • NRC milestone: Construction permits for the Hermes 2 demonstration plant (two 35 MWt molten-salt-cooled reactors, shared power-generation system) issued November 2024.
  • First commercial offtake: TVA-Google-Kairos collaboration announced August 2025. Power purchase agreement between TVA and Kairos to deliver up to 50 MW of 24/7 energy to the TVA grid that powers Google data centers in Tennessee and Alabama. Source: ANS Nuclear Newswire (ans.org); World Nuclear News (world-nuclear-news.org).
  • Google’s broader nuclear position: May 2025 Google announced funding commitments to three advanced nuclear projects. Source: NucNet (nucnet.org).

1.4 Oracle × SMR (three reactors)

  • Disclosure: September 2024 quarterly earnings call. Larry Ellison disclosed Oracle had secured building permits for three small modular reactors to power a gigawatt-class AI data center. Source: CNBC (cnbc.com); The Register (theregister.com).
  • Capacity: >1 GW combined.
  • Disclosure gaps: Ellison did not disclose the SMR vendor, the data-center location, or the regulatory pathway. As of May 2026, no operating-license application has been publicly filed with NRC under Oracle’s name. The “building permits” claim is on the record but unverified in NRC dockets.
  • Context: Oracle has 162 data centers live and under construction globally; the largest existing site is 800 MW.

1.5 Meta × Entergy Louisiana (mixed nuclear/gas/renewable)

  • Site: $10 billion, 4 million+ ft² hyperscale campus in Richland Parish, northeast Louisiana. Largest private investment in Louisiana history.
  • Generation commitment: Entergy will build seven new natural-gas power plants (combined >5.2 GW) plus ~240 miles of 500-kV transmission and battery storage. Three turbines dedicated to Meta will produce 2,200 MW. Source: Tom’s Hardware (tomshardware.com); Entergy press (entergy.com).
  • Solar component: 1,500 MW solar installation commitment.
  • Nuclear component: Meta and Entergy signed an MOU to “explore future development and use of nuclear power” at the site. No NRC application as of May 2026. Source: Data Center Frontier (datacenterfrontier.com).
  • Customer-savings framing: Entergy projects ~$2.65 billion in customer benefit over 20 years; the regulator (Louisiana PSC) has not formally adopted that number.

1.6 Pattern recap

HyperscalerCounterpartyReactor typeCapacityStatus
MicrosoftConstellationExisting LWR restart (TMI-1)835 MWNRC review, 2027 target
AmazonTalenExisting LWR co-located (Susquehanna)up to 1,920 MWFront-of-the-meter PPA after FERC rejected BTM ISA
GoogleKairos / TVASMR (KP-FHR, TRISO)up to 500 MWFirst 50 MW PPA via TVA; reactors 2030+
OracleundisclosedSMR (vendor undisclosed)>1 GWPermits claimed, NRC docket not public
MetaEntergyNuclear MOU (gas + solar today)tbdExploratory

2. US Grid Stress

2.1 PJM Interconnection

PJM serves 65 million customers across 13 states and DC, including the world’s largest data-center cluster (Northern Virginia).

  • Load forecast: The 2025 PJM Long-Term Load Forecast Report projects ~5,250 MW higher peak load for the 2027/2028 Delivery Year vs. the 2026/2027 forecast — of which ~5,100 MW (97%) is attributed to data-center demand. Source: PJM 2025 Load Report (pjm.com).
  • Capacity auction clearing prices:
    • 2024/2025 delivery year: $28.92/MW-day (most zones, pre-AI surge baseline)
    • 2025/2026 delivery year: $269.92/MW-day
    • 2026/2027 delivery year: $329.17/MW-day (all zones)
    • 2027/2028 delivery year: $333.44/MW-day (UCAP, system-wide) Source: PJM auction report (pjm.com).
  • Price-cap effect: Without the FERC-approved price cap, the 2027/2028 capacity price would have cleared near $530/MW-day (~60% higher). Source: Utility Dive (utilitydive.com).
  • Market-monitor finding: PJM’s Independent Market Monitor attributed $6.5 billion (40%) of the $16.4 billion in capacity-market costs from the December 2024 auction to data-center load. Source: Utility Dive (utilitydive.com).
  • Reliability shortfall: PJM procured 145,777 MW in the 2027/2028 auction — about 6,625 MW below its 20% installed reserve margin target. Source: PJM news release (insidelines.pjm.com).

2.2 ERCOT (Texas)

  • Large-load interconnection queue: Grew from ~63 GW (December 2024) to ~233 GW (mid-November 2025). 70%+ of that queue is data centers. Many individual requests exceed 1 GW. Source: ERCOT System Planning and Weatherization Update, December 2025 (ercot.com); Utility Dive (utilitydive.com); Latitude Media (latitudemedia.com).
  • 2030 horizon: Large-load demand seeking interconnection by 2030 grew by 142 GW in 2025 alone. ERCOT generation additions the same year totaled ~23 GW, with another ~9 GW slated for early 2026. The gap (~110 GW) is the load that requests interconnection but has no contracted generation match.
  • Interconnection request volume: 225 large-load requests through mid-November 2025 vs. 152 over the entire 2022-2024 comparable period.
  • Reorganization: ERCOT announced internal structural changes December 2025 specifically citing data-center demand growth as the driver. Source: ERCOT press release (ercot.com).

2.3 CAISO (California)

  • CEC forecast: Data-center load in the CAISO grid forecast to increase by 1.8 GW by 2030 and 4.9 GW by 2040. Source: CAISO Large Load Considerations Issue Paper, January 2026 (caiso.com).
  • Transmission upgrade: May 2025 CAISO approved a cluster of transmission upgrades in the South Bay Area to serve ~2.5 GW of concentrated data-center and electrification load growth (2026-2039).
  • Queue reduction: CAISO reduced Cluster 15 from 541 applications (347 GW) to 145 applications (~68 GW) after a 2025 interconnection-process reform. Source: Zero Emission Grid (zeroemissiongrid.com).
  • Ratepayer concern: California Public Advocates Office October 2025 commentary, “How Will Data Center Growth Impact California Ratepayers?” (publicadvocates.cpuc.ca.gov).

2.4 Northern Virginia (“Data Center Alley”)

  • Loudoun County: ~6,000 MW active capacity, ~6,300 MW planned, as of 2025. Source: Loudoun County government, data-center brief (loudoun.gov).
  • Q1 2025 NoVA total: ~4,900 MW commissioned Northern Virginia data-center capacity, the largest concentration on Earth. Northern Virginia hosts an estimated 35-40% of US data-center capacity by some industry counts.
  • JLARC study: Virginia’s Joint Legislative Audit and Review Commission (JLARC) released its Virginia Data Center Study in December 2024 — the legislative branch’s first formal analysis of the build-out, including cost-shift exposure. Source: JLARC (jlarc.virginia.gov).

2.5 State-level rate-shock cases

Dominion Energy Virginia (DEV)

  • 2025 Biennial Review: Filed by Dominion September 2025 proposing $822 million base-rate increase for 2026 and $345 million for 2027, plus a new dedicated rate class for data centers and other 25+ MW customers (“GS-5”). Source: Virginia Mercury (virginiamercury.com).
  • SCC order (November 2025): Virginia State Corporation Commission approved a smaller increase: $565.7 million for 2026 and $209.9 million for 2027. The SCC also adopted the new GS-5 rate class effective 1 January 2027, with the following contract requirements:
    • 85% minimum monthly payment of contracted distribution and transmission demand
    • 60% minimum on contracted generation demand
    • 14-year contract term
    • Load-ramp period not to exceed 4 years (minimum 20% annual ramp)
    • $350 million in cost recovery removed from Dominion’s request because those projects were in the lower-risk Phase 1 contract bucket. Source: SCC release (scc.virginia.gov); Inside Climate News (insideclimatenews.org); American Action Forum (americanactionforum.org); Southern Environmental Law Center release (selc.org).

AEP Ohio

  • Demand profile: Data-center load in AEP Ohio territory grew from ~100 MW in 2020 AD to ~600 MW in 2024 AD; forecast to ~5,000 MW by 2030.
  • Tariff approval: 9 July 2025. PUCO approved AEP Ohio’s dedicated data-center tariff for new customers with peak demand >25 MW. Provisions:
    • Minimum monthly payment of at least 85% of contracted capacity, regardless of actual energy use
    • 12-year total commitment: 4-year ramp + 8-year minimum
    • Existing facilities grandfathered Source: PUCO; AEP Ohio (aepohio.com); KJK legal analysis (kjk.com); Data Center Frontier (datacenterfrontier.com).
  • Opposition: Amazon, Google, Meta, Microsoft, and the Ohio Manufacturers’ Association filed appeals arguing the tariff was discriminatory. PUCO denied the appeals November 2025. Source: Ohio Capital Journal (ohiocapitaljournal.com); Power Engineering (power-eng.com).

2.6 FERC structural ruling on co-location (Dec 2025)

  • Order: 18 December 2025. FERC directed PJM to establish new tariff rules for co-located large loads and Behind-the- Meter Generation (BTMG) within 90 days, finding the existing rules “no longer just and reasonable.” Source: FERC fact sheet (ferc.gov); Day Pitney legal alert (daypitney.com).
  • New services: Two transmission products proposed — Firm Contract Demand and Non-Firm Contract Demand — to separate cost responsibility between co-located loads and the broader transmission system.
  • Significance: This is the first time FERC has required an RTO to develop standalone tariff rules for the data- center-co-located-with-generation arrangement. Before this order, every nuclear-co-location deal had to be approved one filing at a time on a case-by-case ISA basis.

3. Water Consumption

3.1 Google — 2024 Environmental Report

  • Total data-center water consumption: 8.1 billion gallons in 2024 (Google figure). Source: Google 2025 Environmental Report (sustainability.google); Google blog 2024 Environmental Report (blog.google).
  • Year-over-year change: ~88% increase since 2019.
  • Top single site: Council Bluffs, Iowa data center consumed 1 billion gallons in 2024 — the most of any single Google data center. Source: Google 2024 Environmental Report.
  • Disclosure pattern: Google reports total data-center water consumption; does not disaggregate AI training/inference water use from cloud water use.
  • GHG emissions: Google’s 2023 total emissions rose 13% year-over-year, attributed primarily to data-center energy growth. 2024 data-center electricity consumption rose 27% while data-center emissions fell 12% on a market-based basis (offset by clean-energy procurement of ~8 GW signed in 2024). Source: Google 2025 Environmental Report.

3.2 Microsoft — 2024 and 2025 Sustainability Reports

  • Scope 3 emissions: Rose 30.9% in the FY2024 report (covers fiscal year ending June 2024). Source: Microsoft 2024 Environmental Sustainability Report (Microsoft); Microsoft blog (Microsoft).
  • Total emissions vs. 2020 baseline: +23.4% in FY2024. Scope 3 makes up ~97% of Microsoft’s footprint and has risen ~26% since 2020. Scope 1+2 reduced 30% from 2020.
  • FY2024 → FY2025 change: Total emissions decreased 1.8% year-over-year (15.13 Mt CO2e → 14.86 Mt CO2e). Source: Microsoft 2025 Environmental Sustainability Report (Microsoft); Trellis (trellis.net).
  • Stated cause: Microsoft explicitly attributes Scope 3 rise to “construction of more datacenters and the associated embodied carbon in building materials, as well as hardware components such as semiconductors, servers, and racks.”
  • 2030 carbon-negative pledge: Pledged January 2020. As of May 2026, Microsoft has not withdrawn the pledge despite the +23.4% total-emissions trajectory. Source: Microsoft blog (Microsoft); Sustainability Magazine (sustainabilitymag.com).
  • Clean-energy procurement: 34 GW of carbon-free electricity contracted across 24 countries — 18x the 2020 level. 100% annual renewable-electricity matching achieved in 2025.
  • Water: Microsoft 2024 newest data-center designs use “zero water for cooling” via chip-level cooling solutions — Microsoft’s claim, see Microsoft Cloud blog (Microsoft). This claim has not been independently audited and applies only to the “next-generation” design, not the existing fleet.

3.3 Arizona

  • State context: Arizona Department of Water Resources on-record statement: water “is over-allocated and the groundwater is overcommitted. The amount of groundwater rights issued and the amount we are pumping far exceeds our capacity, and Arizona will not reach its 2025 safe yield goal of preserving groundwater.” Source: Grist (grist.org); PreventionWeb (preventionweb.net).
  • Microsoft Goodyear data center: Public-records requests by reporters were partially redacted: Microsoft argued water consumption figures are proprietary trade secret. Source: Futurism (futurism.com).
  • Municipal pushback: Mesa, Avondale, and Phoenix have passed ordinances capping industrial water usage and requiring developers to purchase supplemental water if they want to exceed those caps. State government has blocked Buckeye and Pinal County from permitting new development that relies on groundwater.

3.4 Texas (Stargate Abilene)

  • Initial fill: 8 million gallons of Abilene city water to initially fill the cooling loop. Source: Texas Monthly, “In Abilene, Stargate AI Is Turning Horse Pastures Into Data Farms” (texasmonthly.com); Crusoe blog (crusoe.ai).
  • Operating consumption: Closed-loop design with air-cooled chillers. Operator (Crusoe) targets ~12,000 gallons per year per building of make-up water after fill. “Zero-water evaporation” is the operator’s stated goal.
  • Tax-revenue dependence: Once fully operational, the facility is projected to deliver up to 32% of Abilene’s and up to 25% of Taylor County’s FY2025 budgeted property-tax revenue. Source: Oracle/OpenAI fact sheet released through Rep. Arrington’s office (arrington.house.gov).
  • Statewide planning gap: Texas state water planners do not yet have a formal accounting of data-center water demand at scale. Source: Texas Tribune (texastribune.org).

3.5 Nevada (Tahoe Reno Industrial Center)

  • Cluster operators: Google, Tract, Switch, EdgeCore, Novva, Vantage, PowerHouse, all operating, building, or expanding within the Tahoe Reno Industrial Center (>108,000 acres, larger than the city of Detroit). Source: MIT Technology Review (technologyreview.com); Data Center Frontier (datacenterfrontier.com).
  • Switch alone: 7.2 million ft² and up to 650 MW; 2,000-acre campus next to the Tesla Gigafactory. Source: Switch (switch.com).
  • Forecasted water use: TRIC data-center-cluster electricity generation could require ~12,450 acre-feet of water annually for upstream generation by 2033, plus ~9,600 acre-feet for direct cooling.
  • Recycled-water solution: Switch and TRIC are building a 16-mile pipeline to deliver recycled water from the Truckee Meadows Water Reclamation Facility — ~5 billion liters recycled water annually targeted. Source: DCD (DatacenterDynamics).

3.6 Disclosure pattern across hyperscalers

NASUCA’s June 2025 Data Centers and Water Use report: the majority of US data centers do not publicly disclose their specific water consumption. Companies routinely redact figures on proprietary or competitive grounds. The CEL Patterns paper (Cell, “The carbon and water footprints of data centers and what this could mean for artificial intelligence,” 2025) found that no hyperscaler currently reports AI-specific water metrics — all reporting is aggregated to whole-data-center level. Sources: NASUCA (nasuca.org); Cell (Cell Press)00278-8); The Invading Sea (theinvadingsea.com (archived)).


4. Compute Concentration

The total US AI compute footprint by capacity, as of end-2025 and the publicly committed pipeline through 2030.

4.1 Stargate (OpenAI / Oracle / SoftBank / MGX)

  • Announcement: 21 January 2025. White House event with President Trump, Sam Altman (OpenAI), Masayoshi Son (SoftBank), Larry Ellison (Oracle). Source: OpenAI (openai.com); Wikipedia consolidation (en.wikipedia.org).
  • Commitment: Up to $500 billion in AI infrastructure through 2029, 10 GW total capacity by end of 2025 (target).
  • Structure: SoftBank financial responsibility, OpenAI operational responsibility, Oracle infrastructure supplier, MGX (UAE sovereign vehicle) co-investor.
  • Abilene, TX (first site): ~10 data centers under construction in Abilene, Taylor County. First building open September 2025. 64,000 NVIDIA GB200 GPUs expected by 2026. Roughly 200 MW first-phase draw, multi-GW build-out target. Source: CNBC (cnbc.com); R&D World (rdworldonline.com).
  • Five additional sites (announced 23 September 2025): Shackelford County, TX; Doña Ana County, NM; Lordstown, OH; Milam County, TX; one undisclosed midwestern site. Brings total announced Stargate capacity to ~7 GW. Source: OpenAI press (openai.com); SoftBank Group press (group.softbank).
  • Oracle additional commitment: $300 billion Oracle compute contract with OpenAI announced September 2025, supplying 4.5 GW under the Stargate umbrella. Source: OpenAI (openai.com).

4.2 xAI Memphis Colossus

  • Site: Former Electrolux factory in South Memphis, Shelby County. Designated “Colossus 1.” Source: Wikipedia (en.wikipedia.org)).
  • Compute: Phase 1 ~100,000 H100 GPUs operational mid-2024; Phase 2 expansion to ~200,000 GPUs end-2024; Colossus 2 targeted 1M+ GPUs.
  • Power: Initial site grid connection insufficient for build-out timeline; xAI deployed a fleet of natural-gas turbines on-site to bridge.

4.3 xAI Memphis turbine controversy

  • Turbines installed: 35 gas turbines, combined ~422 MW capacity. Source: Southern Environmental Law Center (selc.org); CNBC (cnbc.com); Tennessee Lookout (tennesseelookout.com); Inside Climate News (insideclimatenews.org); DCD (DatacenterDynamics).
  • Permits applied for: 15 turbines (~247 MW).
  • Difference: 20 turbines operating without permits, per SELC aerial imagery filed in regulator comment.
  • Emissions: Manufacturer-spec NOx emissions ~1,200-2,000 tons/year — would make Colossus the largest single industrial emitter of NOx in Memphis.
  • Permit issued: July 2025. Shelby County Health Department issued a minor-source air permit for 15 turbines (247.2 MW) valid through January 2027.
  • xAI response (May 2025): Announced plan to pull half the turbines once grid power and on-site Tesla Megapack storage came online. Source: The Register (theregister.com).
  • Community engagement: >2,000 public comments to Shelby County Health Department, majority opposing.

4.4 Project Rainier (Amazon/Anthropic, Indiana)

  • Site: ~1,200 acres near New Carlisle, Indiana.
  • Investment: $11 billion AWS capital. Source: CNBC (cnbc.com); Data Center Knowledge (datacenterknowledge.com).
  • Power: Designed for 2.2 GW build-out — equivalent draw to ~1.6 million homes.
  • Compute: ~500,000 AWS Trainium2 chips at launch (October 2025), targeting 1M+ by end-2025.
  • Anthropic offtake: Anthropic announced new contract October 2025 securing up to 5 GW of AWS capacity for Claude training and serving, including Trainium2/Trainium3 ramping through 2026. Source: Anthropic (anthropic.com).

4.5 US AI compute summary (end-2025)

  • Total US AI-dedicated data-center power capacity: ~30+ GW operational as of mid-2025; ~23 GW additional under construction at end-September 2025 (about 75% of global additions). Source: BloombergNEF (about.bnef.com); Sanchez & Co. GeoCoded report (sanchez.vc).
  • 2027 forecast (RAND): ~68 GW of AI data-center capacity if exponential chip-supply growth continues. Source: RAND (rand.org).
  • 2030 forecast (industry consensus): ~90+ GW US AI compute, ~22% CAGR.
  • GPU census: Approximately 850,000 H100-equivalent GPUs in the US fleet by 2025, vs. ~110,000 in China and ~50,000 in the EU.
  • CapEx: Microsoft + Google + Amazon + Meta committed

    $350 billion combined data-center CapEx in 2025; targeting ~$400 billion in 2026. Hyperscaler total ~$315-320 billion

    1. Source: McKinsey (McKinsey & Company); Sanchez & Co.

5. The Three Mile Island Echo

The reactor that defined American nuclear fear is being restarted to power inference workloads operated by the second-largest equity-economic holder of OpenAI (Microsoft, ~27% on an as-converted basis as of March 2026 — see the financialization dossier section 1.1). This is the load-bearing symbol of the whole buildout.

5.1 The 1979 accident — establishing facts

  • Date: 4:00 AM Eastern Standard Time, 28 March 1979 AD. Three Mile Island Generating Station Unit 2 (TMI-2), a 906 MWe Babcock & Wilcox pressurized-water reactor.
  • Sequence: Loss-of-coolant accident caused by a stuck-open pilot-operated relief valve and operator misdiagnosis. Partial meltdown of the reactor core. Release of radioactive iodine and noble gases.
  • Off-site radiation dose: Average dose to the ~2 million people within 50 miles estimated at ~1 millirem above background (NRC, EPA, DOE consensus). No statistically significant adverse health effects detected in subsequent epidemiological studies.
  • Cleanup: Took ~14 years; cost ~$1 billion (1980s dollars). Sources: Britannica (britannica.com); World Nuclear Association (world-nuclear.org); Wikipedia (en.wikipedia.org).

5.2 Cultural reaction

  • Public-support collapse: Approval of nuclear energy fell from a peak of 69% (1977) to 46% (1979) in Gallup polling. Source: Britannica ProCon (britannica.com); Springer Nature, “Debate about Nuclear Energy” chapter (link.springer.com).
  • September 1979 NYC protest: ~200,000 people. Largest anti-nuclear demonstration in US history to that date.
  • Permitting freeze: No new commercial reactor begun in the United States after 1979 has been completed and brought into commercial operation under its original construction permit. (Watts Bar 2 reached commercial service in 2016, but its construction permit dated 1973.)

5.3 Unit 1 — the surviving reactor

  • Status before shutdown: 819 MW (originally 786 MW pre-uprate, then 837 MW gross / 819 MW net) Babcock & Wilcox PWR. Began commercial operation 1974. Operated continuously for 45 years.
  • Shutdown: 20 September 2019 AD. Economically forced — Constellation (then Exelon Generation) cited inability to compete with subsidized renewables and low natural-gas prices, and the Pennsylvania legislature’s failure to enact a zero-emission-credit subsidy.
  • Restart announcement: Exactly five years later, to the day — 20 September 2024.

5.4 NRC restart process and intervenor activity

  • Filings as of May 2026:
    • NRC license amendment to rename plant: granted 13 May 2025 (Amendment 306, License DPR-50)
    • License amendment to restore Emergency Plan: pending, filed February 2025 (nrc.gov)
    • License amendment to restore licensing basis to operational status: pending, multiple supplements filed through 2025 (nrc.gov)
    • Environmental Report supporting resumption of power operations: filed 31 October 2025
  • License-renewal request: Constellation separately filed for renewal extending plant operation to at least 2054.
  • Intervenors: Three Mile Island Alert (TMIA), founded 1977, led by Eric Epstein. Petition to Intervene filed citing:
    • Absence of off-site emergency plans since 2019 shutdown
    • Absence of radiation monitors since 2019 shutdown
    • “NRC and Constellation lack a historic perspective of emergency planning at Three Mile Island”
    • $1 billion DOE Title 17 loan as federal subsidy Sources: Pennsylvania Capital-Star (penncapital-star.com); WESA (wesa.fm); Lancaster Online editorial (lancasteronline.com).

5.5 Epstein’s deal characterization

Direct quote (Pennsylvania Capital-Star, March 2025): “You’re asking the federal government essentially to subsidize returning a nuclear plant to service. That nuclear power plant will use our labor. It will use our water. The energy will go elsewhere. But we get to keep the waste.”

5.6 Unit 2 — what’s still on site

  • TMI Unit 2 (the reactor that melted in 1979 AD) was defueled by 1990. The remaining radioactive material — primarily damaged-core debris in dry-cask storage and contaminated structures — remains on the site under DOE ownership in an Independent Spent Fuel Storage Installation (ISFSI). DOE filed an amendment application for the TMI-2 ISFSI in February 2026 (Federal Register federalregister.gov) and a separate license amendment notice published 27 April 2026 (federalregister.gov).
  • Symbolic load: When Unit 1 restarts under its new name “Crane Clean Energy Center,” the partial melt-down debris from 1979 will physically remain on the same site, in dry storage, while the adjacent reactor sells 100% of its output to power AI inference at Microsoft data centers in PJM.

5.7 Local water authority debate

The CCEC restart requires a water-use permit from the Susquehanna River Basin Commission. Public comment on the SRBC water-use proposal (2025) drew opposition from residents in Londonderry, Goldsboro, and Middletown — communities that lived through the 1979 evacuation advisory. Source: ABC27 (abc27.com).


6. Energy-Derived Environmental Impact

6.1 IEA “Energy and AI” Special Report (April 2025)

The first comprehensive IEA assessment dedicated to AI energy demand. Key load-bearing numbers:

  • 2025 global data-center electricity consumption: ~485 TWh (data-center output, not AI-only). Source: IEA Energy and AI executive summary (iea.org); IEA World Energy Outlook Special Report (PDF) (iea.blob.core.windows.net).
  • 2030 projected: ~950 TWh — roughly double 2025, ~3% of global electricity demand. Source: IEA Energy Demand from AI page (iea.org).
  • Growth rate: Data-center electricity consumption growing ~15% per year 2024-2030 — more than 4x the growth rate of total electricity from all other sectors. 17% jump in 2025 alone, AI-focused data centers climbing faster than the whole-sector average. Source: IEA (iea.org).
  • AI-only emissions: CO2 emissions from electricity generation for data centers peak ~320 Mt CO2 by 2030, shallow decline to ~300 Mt CO2 by 2035. ~2% of global electricity-sector emissions.
  • Generation mix for the new load: Over the 5-year window, renewables meet ~half of additional demand; natural gas and coal meet most of the rest; nuclear “starts to play an increasingly important role towards the end of this decade and beyond.”

6.2 Lawrence Berkeley National Laboratory — 2024 Data Center Energy Usage Report

Funded by DOE Industrial Efficiency and Decarbonization Office, released December 2024.

  • US data-center electricity 2014: 58 TWh.
  • US data-center electricity 2023: 176 TWh (4.4% of US total).
  • US data-center electricity 2028 (range): 325-580 TWh (6.7%-12% of US total).
  • Growth-rate characterization: Tripled over the prior decade; projected to double or triple again by 2028.
  • Sources: LBNL report (eta-publications.lbl.gov); DOE (energy.gov); LBNL news (newscenter.lbl.gov); CRS R48646 (congress.gov).

6.3 Cell Patterns peer-reviewed paper (2025)

Paper: “The carbon and water footprints of data centers and what this could mean for artificial intelligence” — Cell Patterns, 2025. (Cell Press)00278-8). Findings:

  • Data-center electricity consumption alone accounts for ~1.5% of global electricity demand as of 2024.
  • No hyperscaler currently reports AI-specific water metrics — all reporting is aggregated. This makes it impossible to audit AI-specific water claims against the actual workload mix.
  • Embedded carbon in AI hardware (chips, racks, cooling infrastructure) is a load-bearing component of total emissions and is rarely disclosed.

6.4 The pledge gap

  • Microsoft 2030: Carbon-negative pledge made January 2020. Total emissions +23.4% vs. 2020 baseline as of FY2024; -1.8% YoY in FY2025. Microsoft has not withdrawn the pledge.
  • Google 2030: Net-zero across operations and value chain by 2030. Total emissions +13% YoY in 2023; 2024 data-center energy +27%, market-based emissions -12%. Google has not withdrawn the pledge.
  • Amazon 2040 (“Climate Pledge”): Net-zero by 2040, ten years ahead of the Paris Agreement target. Amazon’s Scope 3 emissions have risen consistently 2020-2025 along with AWS data-center build-out.
  • Meta 2030: Net-zero across value chain by 2030. The seven new gas-fired plants Meta is funding in northeast Louisiana have made meeting this target structurally harder. Sources: Microsoft blog (Microsoft); Sustainability Magazine (sustainabilitymag.com).

6.5 The Carbon Brief framing

Carbon Brief (April 2025) noted that under IEA’s central scenario, data centers’ share of global electricity-sector emissions never exceeds ~2.5% — meaning that as a share of global emissions AI is a smaller story than transport, industry, or buildings, but as a share of electricity-load growth in specific grids (PJM, ERCOT) it is dominant. Source: Carbon Brief (carbonbrief.org).


7. Geopolitical Compute Concentration

The compute is not just concentrated by company — it is concentrated by jurisdiction in ways that have national-security implications. The 2024-2026 cycle is the first in which sovereign-wealth funds, specifically the Gulf SWFs, became named co-investors and counterparty in US frontier-AI infrastructure.

7.1 US geographic concentration

  • Top US clusters (operational capacity):
    • Northern Virginia (Loudoun + Prince William): ~5-6 GW
    • Dallas-Fort Worth: ~2 GW
    • Phoenix metro: ~1.5 GW
    • Silicon Valley + Bay Area: ~1.2 GW
    • Columbus, OH: ~1 GW
  • Top US clusters (announced 2025-2030 pipeline):
    • Abilene, TX (Stargate): up to 1.2 GW first site, 10 GW nameplate across full Stargate pipeline
    • New Carlisle, IN (Project Rainier): 2.2 GW
    • Richland Parish, LA (Meta): 2.2 GW first phase, 7 GW full
    • Memphis, TN (xAI Colossus 1+2): 1.5+ GW
    • Tahoe Reno, NV: 1+ GW industrial-park aggregate
    • Eastern Wyoming, Iowa (Council Bluffs cluster), Tennessee (Google/TVA-Kairos)
  • Federal jurisdictional clusters: The largest concentration of AI inference capacity in the world sits in Loudoun and Prince William Counties — the same counties that host classified government cloud zones for AWS GovCloud, Microsoft Azure Government, and parts of the IC ITE (Intelligence Community Information Technology Enterprise). The geographic overlap between commercial AI inference and federal classified cloud is the load-bearing fact for the state-vendor argument; see AI in State and Local Government.

7.2 Gulf sovereign-wealth concentration

MGX (UAE)

  • Established: March 2024 by Mubadala Investment Company and G42 under the government of Abu Dhabi. Source: Wikipedia (en.wikipedia.org); G42 release (g42.ai).
  • Stated investment scope: AI infrastructure (data centers
    • connectivity), semiconductors (logic + memory), AI core technologies and applications (models, software, data, life sciences, robotics).
  • BlackRock-Microsoft-GIP-MGX AI Infrastructure Partnership: Announced September 2024. Potential $100 billion in US and international AI infrastructure.
  • Stargate equity: Listed by OpenAI as one of the four founding equity funders in Stargate LLC.
  • Anthropic Series G (February 2026): MGX named as a participant alongside GIC (Singapore), Coatue, D.E. Shaw, Dragoneer, Founders Fund, ICONIQ. Series G closed $30B at $380B post. Source: Anthropic press release (anthropic.com).
  • Aligned Data Centers acquisition (October 2025): MGX-AIP-BlackRock-GIP consortium acquired Aligned Data Centers from Macquarie Asset Management for $40 billion. Reported as the largest data-center transaction on record. Source: CNBC (cnbc.com).
  • Stargate UAE: Separate G42-led campus, ~19 km² south of Abu Dhabi. Phase 1: 200 MW compute cluster on NVIDIA Grace Blackwell GB300, online by end-2026. Full build target 1 GW at >$30 billion. Source: DCD (DatacenterDynamics).

HUMAIN / PIF (Saudi Arabia)

  • Established: May 2025. Wholly owned by Saudi Arabia’s Public Investment Fund (PIF). Source: CNBC (cnbc.com); Vision Business Development (visionbusinessdevelopment.com).
  • Predecessor: PIF “Project Transcendence” announced 2024 with $100 billion AI commitment.
  • HUMAIN-NVIDIA partnership (May 2025): Up to 500 MW of data-center capacity, 18,000 NVIDIA GB300 superchips on initial order, “several hundred thousand” more GPUs in the pipeline over five years, target ~600,000 NVIDIA GPUs total. Source: NVIDIA newsroom (nvidianews.nvidia.com); DCD (DatacenterDynamics).
  • HUMAIN-AMD partnership: Additional 500 MW commitment across US and Saudi sites. Source: Seeking Alpha (seekingalpha.com).
  • HUMAIN-AWS partnership: Announced same window.
  • HUMAIN-Qualcomm MOU (May 2025): Edge and cloud AI services.
  • HUMAIN-xAI deal (November 2025): xAI named as anchor customer for a planned 500 MW Saudi data center using NVIDIA GB300 systems. Announced during President Trump’s visit to Riyadh, attended by Jensen Huang (NVIDIA), Elon Musk (xAI), Sam Altman (OpenAI). Source: Bloomberg (bloomberg.com); CNBC (cnbc.com).

Qatar / GIC

  • Qatar Investment Authority (QIA): Participant in xAI Series E (January 2026, $20B at $230B post).
  • GIC (Singapore — separate jurisdiction, included for comparative context): Co-lead of Anthropic Series G with Coatue, February 2026.

7.3 Capital flow summary

The compute-build capital flow as of May 2026:

  1. Frontier labs sign customer/equity deals with Big Tech (Microsoft-OpenAI, Microsoft-Anthropic, Amazon-Anthropic, Google-Anthropic).
  2. Big Tech sources tens-of-billions in additional capital from Gulf SWFs (MGX, PIF/HUMAIN, QIA) to underwrite the data-center build-out.
  3. Big Tech signs contracts with regulated US utilities (Constellation, Talen, Entergy, Dominion) to procure generation.
  4. State PUCs reauthorize rate structures (Dominion GS-5, AEP Ohio data-center tariff) that shift the cost burden from residential and small-commercial ratepayers to the data-center class.
  5. Federal regulators (NRC, FERC, DOE) provide subsidies (Title 17 loans, 45Y tax credits) and create new tariff structures (FERC December 2025 co-location order) to facilitate the build.
  6. Compute capacity becomes physically locked into specific US states (TX, VA, OH, IN, LA, TN, NV) and specific Gulf jurisdictions (UAE, KSA, Qatar).
  7. The companies that operate the compute also hold equity in the labs that train the models that run on the compute, and the SWFs that financed the build hold equity in those same labs.

This is the physical-infrastructure expression of the financialization dossier’s “Microsoft sits on both sides of the principal arm’s-length transactions” finding. The physical-layer finding is even more concentrated: the same handful of governments (US federal, Texas, Virginia, Ohio, UAE, KSA) and the same handful of regulated utilities together control whether a frontier lab can train.

7.4 Trump administration policy posture

  • Stargate launch event: 21 January 2025 White House event with Altman, Son, Ellison.
  • Trump May 2025 Gulf tour: Visit to Saudi Arabia announced HUMAIN-xAI 500 MW partnership; visit to UAE expanded Stargate UAE.
  • EO on data-center permitting: Multiple federal-permit- acceleration executive orders in 2025 specifically targeting the data-center build-out timeline.
  • NRC scope: Title 17 DOE loans (Three Mile Island, others) and 45Y / 45U tax-credit certifications have continued through 2025-2026 across administrations.

9. Open research threads

Items that were partial as of May 2026 and warrant follow-up:

  1. Oracle SMR vendor identity. Ellison’s September 2024 “we have building permits” claim is on the public record. No NRC docket under Oracle’s name corresponds to it. The vendor and site are not yet public. If Oracle’s SMR is NuScale, the only currently NRC-design-certified SMR, that has consequences for the Mountain West (Idaho/Wyoming) siting story. If Oracle’s SMR is X-energy, Kairos, or TerraPower, that places Oracle within the same advanced- reactor cohort as Google/Amazon/DOE.

  2. Trump executive orders on AI infrastructure. Multiple EOs were issued through 2025-2026 specifically accelerating federal permitting for AI data centers and reactor restarts. Pull the specific EO numbers, signing dates, and effected regulatory carve-outs.

  3. TMI-2 ISFSI license amendments. The February and April 2026 Federal Register notices are about the spent fuel from the 1979 melt — same site as the Crane restart. The regulatory-overlap story (DOE-owned debris next door to Constellation-operated commercial reactor next door to Microsoft offtake) has not been told in the press yet.

  4. State PUC cascade. Dominion (Virginia) and AEP (Ohio) are the early templates. Indiana (NIPSCO, AEP/I&M), Georgia (Georgia Power), Texas (PUCT), and South Carolina (SCE&G/ Duke) have data-center tariff dockets in motion as of May 2026. Track which states adopt the 85% / 12-year pattern and which adopt looser/tighter structures.

  5. Gulf SWF disclosure. Mubadala, PIF, and QIA are sovereign and not required to file under US securities laws for private investments below certain thresholds. The full size of Gulf-SWF inflow into US AI compute as of year-end 2025 is not publicly aggregated. Best available secondary source: Crowell & Moring, “The Middle East’s Big Bet on Artificial Intelligence and Data Security” (crowell.com); Middle East Institute primer (mei.edu).

  6. Closed-loop cooling claims. Stargate Abilene, Microsoft next-generation, and other 2025-2026 builds claim “zero-water evaporation” or “zero water for cooling.” These claims are operator-asserted and not yet independently audited at scale. Whether the closed-loop architecture actually scales to GW-class clusters in non-temperate climates (Texas, Arizona, Saudi) is an open engineering question — not yet settled by the literature.

  7. xAI Memphis permit status. The Shelby County Health Department issued a minor-source permit for 15 turbines. The other 20 turbines that SELC documented on-site are not covered. xAI’s stated plan to “pull half” once Megapack and grid power come online has not been verified by ground inspection as of May 2026. Open litigation thread.

  8. Project Stargate location secrecy. The fifth Stargate site announced September 2025 is described only as “midwestern” with location undisclosed. The pattern of undisclosed locations in announcements is worth tracking for the geopolitical-compute chapter.


10. Sourcing-quality note

This dossier prioritizes:

  • Tier 1 (primary regulator/operator): NRC docket filings; FERC orders; PUC filings; SCC orders; IEA, LBNL, EIA reports; hyperscaler 10-Q / sustainability-report filings; named vendor press releases.
  • Tier 2 (specialist trade press): Utility Dive, Data Center Dynamics, Power Engineering, Data Center Frontier, World Nuclear News, ANS Nuclear Newswire, NucNet.
  • Tier 3 (general business press): CNBC, Bloomberg, Reuters, Fortune, Inside Climate News, Tennessee Lookout, Texas Tribune.
  • Tier 4 (advocacy and opposition): Southern Environmental Law Center, Three Mile Island Alert, Clean Virginia, NASUCA, Piedmont Environmental Council. Quoted and attributed; not adopted as editorial framing.

No editorial framing (“guzzling,” “land grab,” “bubble,” “greenwashing,” “scam”) is asserted in this dossier’s voice. Where characterizations are quoted from secondary sources or opposition groups, they are explicitly attributed.


End of dossier.